Which nuclear power companies will achieve criticality before Aug 2026?
Short Answer
1. Executive Verdict
- Kairos Power's Hermes 1 shows rapid licensing and construction progress.
- Most US advanced reactors face significant schedule deficits for 2026 criticality.
- DOE Pilot Program targets three advanced test reactors for 2026 criticality.
- China's ACP100 SMR is deep into its commissioning phase.
- HALEU supply is not an immediate bottleneck for US advanced reactors.
- Valar Atomics achieved criticality; Oklo Inc. reported critical tests in 2025.
Who Wins and Why
| Outcome | Market | Model | Why |
|---|---|---|---|
| Valar Atomics | 69.0% | 3.0% | Research error: Internal Server Error |
| Atomic Alchemy | 59.0% | 3.0% | Research error: Internal Server Error |
| Aalo Atomics | 70.0% | 3.0% | Research error: Internal Server Error |
| Antares Nuclear | 63.0% | 3.0% | Research error: Internal Server Error |
| Oklo | 18.0% | 1.0% | Research error: Internal Server Error |
Current Context
2. Market Behavior & Price Dynamics
Historical Price (Probability)
3. Significant Price Movements
Notable price changes detected in the chart, along with research into what caused each movement.
Outcome: Antares Nuclear
📈 February 22, 2026: 45.0pp spike
Price increased from 52.0% to 97.0%
📉 February 10, 2026: 31.0pp drop
Price decreased from 77.0% to 46.0%
Outcome: Aalo Atomics
📈 February 21, 2026: 11.0pp spike
Price increased from 85.0% to 96.0%
Outcome: Oklo
📈 February 16, 2026: 8.0pp spike
Price increased from 19.0% to 27.0%
Outcome: Valar Atomics
📉 February 08, 2026: 23.0pp drop
Price decreased from 70.0% to 47.0%
4. Market Data
Contract Snapshot
This Kalshi market resolves YES if any nuclear power companies achieve criticality before August 2026. Conversely, it resolves NO if no companies achieve criticality by that deadline. The key deadline for the event is before August 2026, and no special settlement conditions are mentioned.
Available Contracts
Market options and current pricing
| Outcome bucket | Yes (price) | No (price) | Last trade probability |
|---|---|---|---|
| Aalo Atomics | $0.73 | $0.29 | 70% |
| Valar Atomics | $0.71 | $0.31 | 69% |
| Radiant Industries | $0.60 | $0.41 | 65% |
| Antares Nuclear | $0.66 | $0.36 | 63% |
| Atomic Alchemy | $0.60 | $0.41 | 59% |
| Natura Resources | $0.29 | $0.76 | 24% |
| Terrestrial Energy | $0.25 | $0.79 | 21% |
| Oklo | $0.18 | $0.89 | 18% |
| Deep Fission | $0.11 | $0.91 | 11% |
| Last Energy | $0.13 | $0.93 | 8% |
Market Discussion
Debates surrounding nuclear power companies achieving criticality before August 2026 largely center on the ambitious July 4, 2026, deadline set by a US Department of Energy (DOE) Reactor Pilot Program for at least three test reactors [^]. While companies like Valar Atomics claim to have already achieved criticality with assistance from national labs and aim for power operations by the deadline, others like Aalo Atomics are reportedly planning "zero power critical" tests using separate critical assembly facilities, leading to discussions about whether this constitutes "moving the goal posts" for the program's intent [^]. Expert opinions and prediction markets suggest that although many projects are advancing, achieving full electricity-producing operations from these new advanced reactors by the mid-2026 deadline is viewed as highly challenging, with more substantial new-build capacity expected years or even a decade later [^].
5. Which Advanced Nuclear Reactors Can Achieve Criticality Before August 2026?
| Kairos Hermes 1 Construction Permit | December 1, 2023 [^] |
|---|---|
| Kairos Hermes 2 CP Review Duration | 10 months [^] |
| Oklo Initial COLA Denial Date | January 2022 [^] |
6. Will US Advanced Reactors Achieve Criticality by August 2026?
| Major Component Deliveries | None reported to U.S. sites by Q4 2025 [^] |
|---|---|
| TerraPower Natrium Target Operations | Circa 2030-2031 [^] |
| X-energy Component Fabrication Status | Binding reservation agreement signed December 18, 2025; fabrication not yet commenced by Q4 2025 [^] |
7. What is the Current Status of DOE's Advanced Nuclear Reactor Pilot Program?
| Program Criticality Target | July 4, 2026 [^] |
|---|---|
| Valar Atomics Criticality | November 2025 [^] |
| Antares Nuclear Safety Approval | January 2026 [^] |
8. Will China's ACP100 SMR Achieve Criticality Before August 2026?
| Cold Functional Test Completion | October 16, 2025 [^] |
|---|---|
| Non-Nuclear Steam Turbine Tests Completion | December 23, 2025 [^] |
| Official Commercial Operation Target | First half of 2026 [^] |
9. Is HALEU Supply a Bottleneck for Advanced Reactors by Mid-2026?
| Centrus HALEU Production (H1 2026) | 450 kg [^] |
|---|---|
| Unallocated HALEU Inventory (H1 2026) | Zero kg [^] |
| Top 3 Reactor HALEU Demand (H1 2026) | Zero kg [^] |
10. What Could Change the Odds
Key Catalysts
Key Dates & Catalysts
- Expiration: August 08, 2026
- Closes: August 01, 2026
11. Decision-Flipping Events
- Trigger: Potential bullish catalysts include specific achievements from companies like Valar Atomics and Oklo Inc., which announced criticality and critical tests respectively in late 2025 [^] .
- Trigger: A significant driver will be the U.S [^] .
- Trigger: Department of Energy (DOE) Reactor Pilot Program, aiming for at least three advanced test reactors to achieve criticality by July 4, 2026 [^] .
- Trigger: Official announcements from participating companies (e.g., Aalo Atomics, Antares Nuclear, Valar Atomics) confirming criticality before this deadline would strongly impact the market [^] .
13. Historical Resolutions
No historical resolution data available for this series.
Get Real-Time Research Updates
Sign up for early access to live reports, historical data, and AI-powered market insights delivered to your inbox.